Over one weekend in April 2018, TSB Bank moved its 5.2 million customers off Lloyds' proven platform onto a brand-new one, Proteo4UK, in a single event that could not be reversed. The data itself migrated successfully. The platform underneath it was not ready: digital banking failed, the phones collapsed under the overflow, all 550 branches were hit, and the bank did not return to normal until December — more than seven months later. Two regulators later fined TSB a combined £48.65 million. This is the documented story, from the FCA and PRA Final Notices.

Case Studies · Intermediate · 12 min · November 22, 2026

Editorial illustration on a dark teal background: a bank branch building at night with all 550-style windows lit amber in warning, a large padlock on its front door, and two data centre towers behind it with mismatched glowing window patterns.

The short answer

In April 2018, TSB Bank — a UK high-street bank with about 5.2 million customers and 550 branches — switched its entire operation from the Lloyds Banking Group computer platform it had run on since it was created, to a brand-new platform called Proteo4UK, built for it by SABIS, the IT arm of its Spanish parent, Sabadell. The move happened as one big event over the weekend of 20–22 April 2018, and it was designed so there was no way back. The customer data itself moved successfully. Almost everything customers touched did not: internet and mobile banking failed, telephone banking collapsed under the overflow, branch systems ran badly, and some customers were hit by data breaches and payment problems. Every one of the 550 branches and a significant proportion of the 5.2 million customers were affected, and TSB did not return to business as usual until 10 December 2018. In December 2022 the two UK regulators, the Financial Conduct Authority (FCA) and the Prudential Regulation Authority (PRA), fined TSB a combined £48.65 million, finding that the programme had been planned, tested and governed below the standard the law requires.

The company: what TSB Bank did

TSB was a retail bank — the everyday kind: current accounts, savings, mortgages, loans, credit cards and business banking for ordinary people and small firms. It was created in June 2014 by a divestment (a forced sell-off or split) from Lloyds Banking Group, and although it now had its own name, branches and customers, its computers still belonged to Lloyds: TSB ran its core banking on the LBG IT platform under an outsourcing contract.

That contract gave TSB a choice. It could keep using the Lloyds platform for up to ten years, until July 2024. Or it could leave in one of two ways: a carve-out — take a copy of the Lloyds platform and have someone new run the copy — or a full migration, moving everything onto an entirely new platform.

In July 2015 TSB was bought by Banco de Sabadell, a Spanish bank that had a track record of buying banks and moving them onto its own banking platform, called Proteo. A key reason for the takeover was the expected saving from moving TSB onto Proteo too, and the aim was to finish the migration by the end of 2017. The British version — Proteo4UK — would not be the proven Spanish system lifted across. Per the regulators, it was a newly built version, created largely from the Spanish platform but needing significant customisation for the UK market. It would be designed, built and tested by Sabadell's IT subsidiary, SABIS, which would also run it after the move. SABIS in turn relied on 85 third-party suppliers to deliver pieces of the system.

Why this matters: TSB was, in the PRA's words, the first major bank in the UK to attempt a migration of this scale and complexity — a predominantly single-event move, to a newly built and unproven platform, with new data centres, run by a supplier with no experience of managing delivery from large numbers of UK subcontractors. And once it left the Lloyds platform, there was no road back.

The problem: a one-way door, opened on a deadline

Nothing here was an attack or a freak accident. The risk was built in, layer by layer, over two years — and the regulators' notices describe each layer.

The timetable was set before the work was understood. TSB adopted its Integrated Master Plan in March 2016, with the main migration first set for 5 November 2017. The PRA found the programme fell behind from the outset. On 20 September 2017 TSB accepted it had to re-plan — yet nine days later, before the re-planning was even finished, it publicly announced the migration would now happen in the first quarter of 2018. The new plan (the Defender Plan) was approved on 24 October 2017. It quickly fell behind too, and the FCA found that guiding principles meant to protect the programme were departed from, banking features were deferred until after the move or replaced with manual workarounds, and testing was squeezed to hold the date.

The supplier was family, so nobody checked it could do the job. SABIS was part of the same group, and the FCA found TSB never carried out a formal, comprehensive due-diligence exercise (a structured check of capability before trusting someone with critical work) on whether SABIS could deliver and operate Proteo4UK in the time allowed. TSB also worked without proper design documentation: it accepted configuration documents instead — paperwork that, as the FCA put it, could not be used to verify the platform had actually been built to the original design — and in February 2018 it decided not to require the full set even of those.

The testing that mattered most was cut. Testing ran late, phases that were meant to run one after another ran in parallel or changed scope, and testing only finished the day before the decision to migrate was taken. Most importantly, non-functional testing — testing how the system behaves under real-world load, for example how many customers can log into the mobile app at once — was reduced in scope around the end of February 2018. The cut removed testing of the digital channels in Active-Active configuration, the setup where both data centres share live traffic at the same time. The FCA's finding is blunt: had that testing been done, it is likely the configuration problem in the data centres — the fault that later made internet and mobile banking unavailable — would have been found. The decision was taken outside the proper governance forum, and the risks of not testing were never identified or reported upward.

There was no plan for it going badly wrong. Because the migration was irreversible, a major incident would leave TSB stuck on the new platform, dependent on SABIS to fix multiple faults at once. Yet its incident playbooks were designed to support only the first 48 hours, and its practice exercises assumed incidents would be resolved within a few days. The FCA found TSB had not prepared for a multiple-incident crisis of the scale that actually happened — including how to communicate with customers, how to scale up complaint handling, or how to protect vulnerable customers through a long incident.

An analogy: this is moving house by burning the old house down on a fixed date announced in the newspapers — before checking the new house has working wiring, and after skipping the one inspection that would have tested the wiring under full load.

One weekend, one direction, no way back BEFORE — LBG PLATFORM Proven, stable, scalable TSB could have stayed until July 2024 Ran TSB since its creation in 2014 AFTER — PROTEO4UK Newly built, unproven at this scale New data centres, 85 third parties Built and run by SABIS (Sabadell group) 20–22 APR 2018 5.2m customers rollback: none — migration was irreversible The data moved successfully. The risk was never the data — it was whether the new platform underneath it had been proved under real load, in the configuration customers would use. A one-way change demands more proof before it, not less. TSB had less.

What this shows: the shape of the bet. A proven platform TSB could have stayed on for six more years was exchanged, in a single weekend, for an unproven one — with the return path closed by design.

What happened: the weekend of 20–22 April 2018

The regulators call the move the Main Migration Event. The Board approved serving notice to leave the Lloyds platform on 10 April 2018, approved the final readiness pack on 18 April, authorised the start on 19 April, and the migration began on 20 April.

From one weekend to eight months 20–22 April 2018 — the Main Migration Event Data migrates successfully; from an early point after go-live on 22 April, serious failures appear First week — extensive disruption on every channel Digital, telephone, branch and card problems; all 550 branches affected May 2018 — Putting Things Right Programme starts Extra staff and third parties brought in to handle complaints and pay redress 10 December 2018 — back to business as usual 20 December 2022: FCA and PRA fine TSB a combined £48.65 million

22 April 2018, go-live. From an early point after the system went live, the FCA records, TSB hit serious issues: certain data breaches (some customers could see information that was not theirs — the class of failure the notices record without naming individuals), failures in digital banking (internet and mobile), failures in telephone banking, branch technology failures, and knock-on problems with payments and debit cards — even though, the PRA notes, the underlying payment systems themselves were functional.

The cascade. When one channel fails at a bank, customers do not disappear — they move. The FCA describes the chain exactly: digital failures pushed customers to telephone banking; call volumes hit unprecedented levels while telephony itself had IT problems, so wait times soared and many customers abandoned calls; customers who could use neither channel queued in branches, where systems were also running slowly under the extra demand. Every fallback channel was degraded by the same root incident, so there was nowhere healthy for demand to go.

The cascade: every escape route led to the same fire 1 · DIGITAL FAILS Internet and mobile banking unavailable for periods — a data- centre configuration fault 2 · PHONES OVERLOAD Customers switch to telephone banking — unprecedented call volumes, plus its own IT faults 3 · BRANCHES QUEUE Long queues build in busy branches — whose systems are also running slowly One incident, three channels down together. A fallback only works if it does not share the failure — and if it has the capacity for everyone the failed channel sends it. TSB planned for bumps in the road. It got a multi-week, multi-incident crisis instead.

What this shows: the failure chain the FCA describes. Digital failed first; the demand did not vanish, it moved — and each channel it moved to was weakened by the same incident and sized for normal days, not for carrying the whole bank.

The long tail. Disruption was extensive through the first week, and problems continued in the following days and weeks, with more limited issues persisting for months. The direct technical causes, per the FCA, substantially related to IT configuration, capacity and coding. There was no rollback to reach for: TSB was on Proteo4UK now, and SABIS had to fix it in place. TSB did not return to a business-as-usual position until 10 December 2018 — over seven months after the migration weekend.

The damage

The human measure comes first in the notices. Between 22 April 2018 and 7 April 2019, TSB received 225,492 complaints about the migration — about 4.3 percent of its entire customer base — and it took almost twelve months to work through them. The FCA records that some customers suffered significant detriment (real financial or personal harm), including vulnerable customers for whom the bank's systems had known limits in even identifying them during an incident.

The money TSB paid directly to customers was £32,705,762 in redress over that period — refunds, expenses, distress and inconvenience payments, and putting customers back in the position they should have been in. (Later reporting put the bank's wider programme costs far higher; those totals do not appear in the regulators' notices, so this case does not print them.)

Then, four years later, the regulatory bill. On 20 December 2022 the FCA fined TSB £29.75 million for breaching its Principles 2 and 3 — failing to act with due skill, care and diligence, and failing to organise and control its affairs with adequate risk management. The PRA fined TSB £18.9 million for breaching its Fundamental Rules 2 and 6 across 16 December 2015 to 10 December 2018. Both fines carried a 30 percent settlement discount; without it, the combined penalty would have been £69.5 million instead of £48.65 million.

How they recovered

There was no technical shortcut, because there was no old platform to return to. Recovery meant fixing Proteo4UK in production, in public, while customers were watching.

Step one: own the customer harm. On 24 April 2018 — two days after go-live — TSB published the assurance that no customer would be left out of pocket as a result of the service issues. That promise shaped everything after: the bank would make customers whole first and argue about causes later.

Step two: build a machine for putting things right. In May 2018 TSB set up its Putting Things Right Programme to handle the fallout, bringing in additional staff and third-party help to process the 225,492 complaints and pay the £32.7 million in redress. The scale of that operation is itself a finding: complaint handling had been planned for ordinary volumes, and the programme had to be invented mid-crisis because the contingency planning the regulators later criticised had not covered an incident of this size.

Step three: grind back to normal. Faults were fixed one by one on the live platform over the following months — the FCA notes many post-migration events took weeks to resolve, against playbooks written for 48 hours. Business as usual was only declared on 10 December 2018. The enforcement outcome then closed the loop in December 2022, with the two Final Notices setting out, in public, exactly which planning, testing, governance and outsourcing duties had been breached.

The fix: technology and controls that came out of it

The two notices read as a checklist for anyone planning a migration that cannot be undone. Each item below is a failure the regulators named, stated as the control it demands.

Test the configuration customers will actually use, at the load they will actually create. The single most expensive skipped test was non-functional testing in Active-Active configuration. A platform split across two data centres behaves differently when both halves carry live traffic together — that is exactly when a configuration mismatch between them shows up. The rule the case leaves behind: if a test is the only one that can find a class of fault, cutting it is not a schedule decision, it is a risk decision — and it must be taken in the proper forum, with the risk of not testing written down and owned.

Never let a deadline outrank the evidence. TSB announced its re-planned date publicly before the re-plan existed, then protected the date by running tests in parallel, deferring features and accepting manual workarounds. Each individual compromise looked small; the regulators' point is that nobody added them up and re-asked the only question that mattered: given everything we have cut, is this still safe to do irreversibly? Deviations from an agreed plan have to change the risk assessment, not just the plan.

Do due diligence on your supplier even — especially — when it is family. TSB and SABIS shared a parent and aligned commercial interests, and the PRA is explicit that this did not remove the outsourcing risk. TSB never formally assessed SABIS's capability at the start, never got design documentation it could verify the build against, and never ensured it could see the risks in the 85 fourth-party suppliers underneath SABIS. The control: the firm doing the regulated activity keeps the duty. Outsourcing the work never outsources the accountability, and an intragroup badge is not evidence of capability.

Plan the bad day at the scale of the change, not the scale of a normal incident. A 48-hour playbook for an irreversible migration is a category error. Business-continuity planning has to assume the plausible worst case the change itself creates: multiple simultaneous incidents, weeks not days, every channel degraded at once, complaint volumes an order of magnitude above normal, and a customer-communications and vulnerable-customer plan that works under those conditions — rehearsed, not just written.

Capacity is a channel-failure control. The cascade was a capacity story as much as a software story: telephony and branches were sized for the demand they normally see, not for the demand a digital outage sends them. Any channel that acts as the fallback for another channel must be load-planned for the day the primary fails completely.

What this means for you

Enterprise network and platform engineers

This is your change-management cautionary tale, and the details translate directly. Two data centres specified to work together were carrying a configuration fault that only the skipped Active-Active test would have exposed — the infrastructure version of configuration drift between supposedly identical nodes. The habits that prevent it are unglamorous: verify both sites are actually configured the same, load-test the real failover and load-sharing mode (not a simplified stand-in), and treat any proposal to cut that test as a formal risk acceptance with a name on it. And before any one-way change — a core migration, a routing-platform swap, a data-centre exit — write the answer to one question in advance: if this goes wrong at hour two, what exactly do we do at hour three, day three, and week three?

Hyperscaler engineers

Your migrations are usually gradual — canaries, waves, dual-running — and TSB is the argument for keeping them that way. A predominantly single-event migration concentrates all risk into one weekend and removes the option to learn from the first one percent of traffic. Where a big-bang step is genuinely unavoidable, TSB shows the minimum bar: the full production configuration tested at full production load, a rehearsed multi-week incident plan, and fallback channels capacity-planned for total primary failure. It also shows why "the data migrated successfully" is the wrong success metric — data movement is the easy half; the platform's behaviour under real users is the migration.

Try it yourself

The fault that hurt TSB most was a configuration problem between two data centres that were supposed to work as one — the kind of mismatch that only shows up when you compare configurations side by side instead of trusting that they match. Practice that habit free with Packet Path's Network Config Verifier: paste two device configs and it flags inconsistencies automatically. For a bigger picture, the Config-to-Topology Mapper turns pasted configs into an interactive topology with mismatch findings — a quick way to see whether a network that is supposed to be symmetric actually is.

Sources

Primary source — Financial Conduct Authority, Final Notice to TSB Bank plc (20 December 2022). The migration programme, testing, outsourcing and business-continuity findings, the incident description, complaint and redress figures, and the £29.75 million penalty are taken from this notice: https://www.fca.org.uk/publication/final-notices/tsb-bank-plc-2022.pdf

Primary source — Prudential Regulation Authority (Bank of England), Final Notice to TSB Bank plc (20 December 2022). The programme governance, planning and readiness findings, the 550-branch impact statement, and the £18.9 million penalty (reduced from £27 million) are taken from this notice: https://www.bankofengland.co.uk/-/media/boe/files/prudential-regulation/regulatory-action/final-notice-from-pra-to-tsb-bank.pdf

Bank of England news release, "TSB fined £48.65m for operational resilience failings" (20 December 2022) — the combined £48.65 million total, the £32.7 million redress figure, and the regulators' summary statements: https://www.bankofengland.co.uk/news/2022/december/tsb-fined-for-operational-resilience-failings

Scope note: these notices do not publish a count of individual customers locked out, a total programme cost, or a fraud figure, so this case prints none. Figures quoted elsewhere from the separate Slaughter and May review commissioned by TSB are not used here.

Key takeaways